Excavation & Cut–Fill Studio Pro

Survey-based earthwork quantity estimation, project reports and Excel workflows in one workspace.

Three calculation methodsEditable measurement recordsExcel & CSV reports
EARTHWORK CALCULATIONS3 Methods

Average End Area · Prismoidal · Spot Grid

← Back to Construction Tools

Project setup

Define measurement units and volume adjustments before calculating.

01 · CONFIGURATION

Cut and fill factors are user-defined multipliers applied separately to raw volumes. An adjusted cut–fill balance is meaningful for material reuse only when both factors are expressed on the same basis.

Cross-section area records

Enter chainage and independently measured cut/fill areas.

02 · INPUT DATA
Stations must be strictly increasing. Midpoint cut/fill areas are required for the Prismoidal method.
Ready. Enter measured values or load a demonstration project.

Calculation report

Interval-by-interval quantities, cumulative totals and exportable audit trail.

04 · REPORT
Calculate to generate a quantity report.

Method, units, factors and timestamp are included in exported reports.

Calculation basis

Average End Area: V = L × (A₁ + A₂) ÷ 2 for cut and fill calculated separately.

Prismoidal: V = L × (A₁ + 4Aₘ + A₂) ÷ 6. Midpoint areas must come from a surveyed middle section.

Grid: Each four-corner cell is divided into triangles; positive and negative level differences are integrated separately to avoid cancelling mixed cut/fill.

Survey & safety checks

Use the same vertical datum, consistent chainage and non-overlapping grid areas. Section area plots are schematic and do not reconstruct real cross-section profiles.

Assumes straight-line interpolation of elevation difference between cell corners; validate against drawings, survey boundaries, earthwork specifications and field measurements.

Values are calculated locally in your browser. Excel imports require an external worksheet reader when using .xlsx; CSV and JSON imports work without it.